2020 Construction Update

Picture
​Brisbane Islamic Centre Ltd (BIC) would like to update the community on progress to gain the building approval (BA) required for construction of the project to commence.

The status of the Mosque and Community Hall development is that a Development Approval  (DA) was obtained through an appeal process, in the Planning and Environment (P&E) Court in early 2017.
​Tree clearing and earthworks commenced late 2017 and was completed by mid-2018.
During these earthworks it was discovered that the water table was higher than expected and the plans that were approved by the court needed to be amended. This amendment meant that the building required to be raised proportionally to mitigate the water table issue.
​Currently our application to amend the ground level and some changes to the building is referred to as a “Minor Change Application.” This application has now been lodged in the P&E Court and Insha-Allah in early 2020 we expect this application to be approved.
​
Picture
The BIC site cleared and leveled

​In tandem with the above process we engaged consultants to prepare Building Approval (BA) plans. These plans will need to be approved by a private certifier and does not require the council approval.
The BA stage is a process by which detailed plans are prepared for construction. This would include engaging a project / design manager and consultants namely for civil, architectural, electrical, hydraulic, mechanical, fire, traffic, environment, acoustic and finally a certifier.
 
This indeed is the lengthiest part of the BA process and we have to date completed some 80% of this with the expectation that it would also be completed by the first half of 2020. More than $500,000 has been spent on this process in the last two years.
 
Insha-Allah once the Minor Change and Building Approvals are obtained, we expect construction to commence soon thereafter. Expected time frame is between March and June 2020, and the project is expected to be completed within 3 years.
 
Background
 
The land was purchased in 2007, after which it was donated Waqf to the community within an established Trust structure. The Centre will be situated on approximately 4.5 acres of the 10-acre site in Eight Mile Plains, Brisbane in Queensland. The investment to date is in excess of $3 million and the property is unencumbered.  
 
The land use is separated by the creek into 2 blocks:

  1. Stage 1 is approximately 4.5 acres and is dedicated to the Musjid / Community Centre project and is situated on the southern portion.
  2. Stage 2 is approximately 4.5 acres situated on the northern portion and is dedicated to a retirement village, aged care facility, medical centre and a childcare facility.
 ​
Picture
​Stage One - Musjid & Community Centre
 
The Masjid to accommodate over 2500 men, ladies  and children, an office block, dedicated dawah facilities (including a 120-seater audio visual theatre, Islamic museum, library),  community hall with a capacity to cater for over 750 people and parking for 400 cars.
 
The office block will have serviced offices for community organisations that would include a common boardroom. Further features of the Centre will be a cafeteria, outdoor dining, madrassa, separate youth facilities for boys and girls.
 
An important component of the project is the maintenance and enhancement of the Bulimba Creek environment that runs through the centre of the block.
 
The process of raising funds and donations from the community will commence early next year, Insha-Allah
​
​Stage Two – Retirement Village, Medical Centre and Child care
 
This will be situated on the northern part of the 10 acre property, fronting Underwood road.
A development application was lodged with the Brisbane City Council at the end of November 2019. The process and time for council to consider this application and approve it can be between 12- 15 months.
 
The Centre is designed to include:
  • 91 x 1 and 2-bedroom retirement units
  • 20 Aged/frail care units
  • 10 units for dementia care
  • A 250 square meter medical Centre
  • A 75-place childcare centre.​​
Picture
Picture
Physical Address:
161 Underwood Road
Eight Mile Plains, Brisbane
Queensland, Australia 4113.
Mobile: 
0468 825 786
​E: secretary@bic.org.au 
Postal Address:
Brisbane Islamic Centre
PO Box 250
Underwood, Brisbane
Queensland, Australia 4119.
​​
Bank Account:
Brisbane Islamic Centre
Suncorp Bank
BSB: 484 799      
​
A/c No: 480 458 040
METWAU4B (Swift code for transfers from overseas)

Office Use Only
BIC Ltd © 2018
  • About BIC
  • Masjid Complex
  • Construction
  • Project Funding
  • Sukoon Village
  • UPDATES
    • Open Day
    • Soil Turning Event
    • Gallery
  • Donate Now
  • Contact Us